Weekly Executive Status (Template)
This format is designed to prevent “green-by-default” reporting. It prioritizes outcome evidence, decisions needed, and what happens if a risk materializes.
1) Summary
| Overall RAG | 🔴 Red (example) — critical readiness evidence missing for peak channel stability |
|---|---|
| This week’s focus | Pass peak performance criteria; complete rollback rehearsal; finalize ops surge model |
| Steering decisions required | Approve extension of readiness window OR accept risk with documented rationale |
2) Readiness by area
| Area | Status | Evidence | What it means for customers | Ask |
|---|---|---|---|---|
| Data reconciliation | 🟡 | Dry run complete; independent verification pending | Potential incorrect balances if exceptions not resolved | Approve additional verification cycle |
| Peak channel stability | 🔴 | Intermittent failures under load in dress rehearsal | Customers may be unable to log in / view accounts | No-Go unless pass criteria met |
| Payments continuity | 🟡 | Critical paths tested; exception scenario pending | Standing orders / transfers may fail | Require exception scenario proof |
| Ops surge plan | 🟡 | War-room defined; staffing gaps to be confirmed | Slow support response during incidents | Confirm coverage + triage ownership |
| Rollback readiness | 🟡 | Plan documented; rehearsal scheduled | Longer outage if rollback fails | Complete rehearsal before Go/No-Go |
3) Top risks
- Channel failure under peak load: mitigate with performance tuning + re-test + hard gate
- Data mismatches: mitigate with reconciliation + independent validation
- Ops overload: mitigate with surge staffing + triage model + comms updates
4) Decisions log (this week)
| Date | Decision | Owner | Rationale |
|---|---|---|---|
| — | Example: Extend readiness window by 7 days | Steering Committee | Outcome evidence not met; protect customers + resilience |
A status report is not a performance summary. It’s a decision instrument.