Lessons Learned
What worked
- Integrated scheduling surfaced “portfolio truth” earlier than individual trackers
- Near-critical monitoring reduced surprise slippage even when dates looked stable
- Dependency ownership + next-step discipline improved closure rate
- Sensitivity scenarios made tradeoffs explicit (and decisions faster)
What I’d improve next time
- Lock evidence standards earlier (what counts as “confirmed”)
- Reduce churn by tightening change-control thresholds
- Strengthen readiness definitions for commissioning and handover
A schedule can be correct in isolation and still be wrong in context. The IMS is how you protect committed delivery dates from hidden drift.