Weekly Business Review (WBR) – Schedule
Week summary (sample)
- Status: Amber
- Headline: Forecast stable, but float erosion on power approvals is increasing committed-date risk.
- Decisions needed: surge support + approval escalation pathway
Progress (highlights)
- IMS refreshed; critical/near-critical list published with owners
- Two dependency closures confirmed with dates and evidence
- Commissioning pre-work pulled forward to protect end-to-end chain
Critical tasks next 2 weeks
- Utility approval confirmation + energisation window locking
- Network integration slot confirmation for Site Cluster B
- Commissioning readiness checklist completion and sign-off
Risks / blockers
- Approval lead time volatility (requires escalation)
- Vendor delivery variance on long-lead components
Next steps
- Run sensitivity scenario refresh for power delay (+10 working days)
- Publish recovery plan options with tradeoffs
- Confirm decision date with stakeholders to avoid late-stage churn