Project Charter

Formal programme mandate, strategic alignment and governance approval framework

1. Programme Background

The West Dublin manufacturing campus operates a sterile biologics facility supplying EU and US markets. Site utilisation exceeded 90% capacity following expanded therapeutic indication approval for a high-volume monoclonal antibody product.

Network capacity analysis identified upstream bioreactor constraints and downstream purification bottlenecks, creating a projected 18–24 month supply risk without expansion.

The expansion programme was initiated to protect commercial continuity, maintain regulatory compliance, and secure long-term manufacturing resilience.

2. Strategic Alignment

3. Business Case Summary

Capital Investment €180 Million
Capacity Increase +38% Upstream Output
Revenue Protection €180M Annually
Break-even Period 3.5 Years
Net Present Value Positive (Confidential)
Inspection Requirement EU GMP + FDA Approval

4. Programme Objectives

5. Scope Definition

In Scope:

Out of Scope:

6. Governance Structure

7. Stakeholder Matrix

Stakeholder Role Influence Engagement Model
Global Manufacturing Capital Approval Authority High Monthly Executive Review
Site Operations Production Continuity High Weekly Steering
Quality Assurance Compliance Oversight High Risk Committee Cadence
Engineering & Automation Technical Delivery Medium Integrated Master Schedule Governance
Regulatory Authorities Inspection Approval Critical Pre-inspection Engagement

8. Assumptions

9. Constraints

10. Milestone Plan

URS Approval Month 3
Detailed Design Freeze Month 6
Equipment FAT Complete Month 12
Mechanical Completion Month 17
IQ/OQ Execution Complete Month 20
PQ Complete Month 22
Regulatory Inspection Month 23
Commercial Release Month 24

11. Critical Success Metrics

12. Approval

This charter represents formal authorisation to proceed with the capital programme subject to stage-gate financial governance and regulatory compliance requirements.