Schedule Overview
The Integrated Master Schedule contained over 3,200 line items and 400+ cross-stream dependencies. The critical path ran through bioreactor fabrication, utilities revalidation, PQ execution and inspection readiness.
Schedule Control Techniques
- Float Analysis
- Near-Critical Path Monitoring
- Contingency Buffers
- Parallel Workstream Compression